Eskom downgrades loadshedding to stage five

Eskom announced on Monday that it will implement stage five of rolling blackouts from midnight after Camden, Kriel, Kusile and Kendal power plants returned to service.

However, it said, a unit at Duvha had to be taken off after it developed a boiler tube leak. The power utility suffered a double blow of failing units at the Kusile and Kriel power plants which necessitated stage six rolling blackouts on Sunday.

It is still unclear how long stage five will last.

Meanwhile, many areas in Gauteng have reported power outages outside of their loadshedding schedules, leaving residents frustrated.

“Overnight a unit each at Camden, Kriel, Kusile and Kendal were returned but unfortunately had to take off a unit at Duvha which developed a boiler tube leak. Loadshedding will thus be reduced to stage five at midnight.”

A fire had also broken out, impacting a conveyor belt at Kriel mine. Eskom said this was not at the power station and has no effect on the power station as it is receiving coal from an open pit and by road.

 

Also read: DA calls on Gauteng premier Makhura to address loadshedding

To read more political news and views, click here.

Follow @SundayWorldZA on Twitter and @sundayworldza on Instagram, or like our Facebook Page, Sunday World, by clicking here for the latest breaking news in South Africa. To Subscribe to Sunday World, click here.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

[jetpack-related-posts]

Latest News